Belagavi-Panjim route via Chorla set for smoother travel as Kusmalli bridge nears completion before monsoon.

The Belagavi-Panjim route via Chorla is on track for a major transformation, with road upgrades in their final stages and the Kusmalli bridge construction progressing at full speed to ensure completion before the monsoon.
The century-old bridge over River Malaprabha, which once symbolized connectivity between Belagavi and Goa, was demolished in January due to its deteriorated condition. Now, a broader and taller bridge is being built to accommodate smoother traffic movement and enhanced connectivity.
Completion Timelines on Track
According to NHAI Project Director Bhuvanesh Kumar, the new Kusmalli bridge is set for completion by mid-May, ensuring it is ready before the monsoon swells River Malaprabha. Meanwhile, the first layer of asphalting has been completed on the 43.5 km Kinaye-Chorla stretch, with 10 km of the second layer also finished. The entire Chorla Road upgrade is expected to be completed by mid-April.
“The first layer of asphalting, Dense Bituminous Macadam (DBM), has been laid across the entire Kinaye-Chorla stretch. The second layer, known as the wearing course, is now being applied for smoother and more durable travel,” Kumar stated.
He also confirmed that Belagavi Deputy Commissioner Mohammed Roshan is closely monitoring the project to ensure timely completion.
Chorla Road Becoming a Preferred Route
For over a decade, travelers faced deteriorating road conditions on the Belagavi-Goa highway. Now, with major improvements underway, the route is rapidly gaining preference, leading to a steady increase in Karnataka travelers to Goa.