As temporary repairs of stretches is not going to resolve the long pending issue, people from Belagavi and Goa are demanding authorities from both states to take up the matter with Union Minister Nitin Gadkari . Gadkari in February 2022 had laid the foundation for widening of the Jamboti -Sanqelim road amid much fanfare.
According to the contractor who repaired the damaged stretches in May, out of the 1.6 kms that was repaired a 30-meter stretch near Delta Hotel and 25 meters stretch near the Karnataka excise check post were damaged. “ The water at these spots was stagnated due to which road is damaged. Due to forest restrictions, there is no provision to drain the water “ site engineer Imran Odekar who is supervising the repairs of the damaged stretches said. Laborers were filling the potholes and using loaded hammer to reinforce the same.
However, the question of the other damaged stretches continued to haunt the travelers as the major stretches of the road have become difficult to travel. When contacted NHAI project director Bhuvanesh Kumar said that though the road was repaired several times, due to heavy rains it is damaged again. “We repaired it several times but due to heavy rain, it has again been damaged. Will take up for rectification for motorable condition immediately,” Bhuvanesh Kumar told .
He also lamented the delay of implementation of the much-touted two-laning work that was inaugurated by Union Minister Nitin Gadkari in February 22 .
“ We couldn’t attend all the locations as the estimate was prepared considering that widening work will be started but unfortunately widening work contract had to be terminated. At a few locations where repair has been done recently, there is some damage which we have asked the contractor to attend continuously and after the rainy season to rectify it permanently,” Bhuvanesh Kumar ascertained.
……….. End
Photo : Workers of the contractor repairing the damaged stretch of Chorla Road between Kankumbi and Chorla.
Louis Rodrigues