Traffic movement on the busy Belagavi-Goa route via Chorla Road, which has been disrupted since late Sunday, is expected to resume this Thursday as the National Highways Authority of India (NHAI) completes the insertion of additional pipelines at the Malaprabha River diversion near Kusmalli.
The route was affected after the temporary diversion near the old Kusmalli bridge partly caved in last week due to a sudden rise in the Malaprabha River’s water level caused by incessant rainfall. This led to the diversion of vehicles via Khanapur, adding approximately 15 kilometers to the journey for commuters traveling between Belagavi and Goa.
“Earlier, only two pipelines were in place, which couldn’t handle the excess water flow. We’ve now added two more pipelines to manage the increased water volume,” said NHAI Executive Engineer Rajendra. He confirmed that vehicle movement through Kusmalli would resume from Thursday.

Rajendra also noted that the construction of the new bridge at Kusmalli is progressing well. “The concrete slab on one side is complete. The remaining slab will be laid on June 30, following which the bridge will be open for regular two-way traffic,” he added. The bridge is designed to be 12 meters wide, ensuring smooth movement in both directions.
Currently, only two-wheelers are allowed to pass through the bridge, as water levels continue to recede. Four-wheelers and heavy vehicles remain restricted due to ongoing safety assessments.
NHAI Project Director Bhuvaneshwar Kumar is personally overseeing the project to ensure timely completion and safer travel for commuters.