Traffic on the key Belagavi-Goa Chorla Road has resumed through the Kusmalli bypass from Wednesday evening, allowing movement for all vehicles, including four-wheelers, after days of disruption due to heavy rains and damage to the temporary diversion near the Malaprabha River.
The route had been closed since late Sunday after the temporary bypass near the old Kusmalli bridge partially collapsed due to a sudden surge in river water levels. Commuters had to reroute via Khanapur, resulting in an additional 15 km of travel.
To address the issue, the National Highways Authority of India (NHAI) inserted additional pipelines to manage the increased water flow. “Earlier there were only two pipelines which couldn’t handle the heavy inflow. Two more have now been added to stabilize the bypass,” confirmed NHAI Executive Engineer Rajendra.
Work on the new 12-meter-wide bridge at Kusmalli is also progressing. “One side of the concrete slab is complete. The remaining slab will be laid by June 30, after which the bridge will be open for full two-way traffic,” he added.
NHAI Project Director Bhuvaneshwar Kumar is overseeing the work to ensure timely completion and public safety. While all vehicles are now allowed on the bypass, authorities are continuing to monitor safety conditions closely, especially for heavy vehicles.